Approval documents available include both orders and explanatory cover letters for: waterflood (pressure maintenance), gas injection, innovative technology (experimental), Good Engineering Practice, disposal wells, observation wells, Concurrent Production, commingled production, and gascap blowdown.

These records span from 1964 to present-date and include any amendments made to an approval, as well as denial letters. Applications for these approvals may be requested by submission of a well data request form. The company name is that at the time of correspondence, and may not reflect the current well permit holder. The filter function allows partial entry of a single data field as search criteria.


3684 items

Sort: Title / Date

 

CONCURRENT GEP CNRL Buick Creek Lower Halfway 'K' Amend 1 Apr-06-98 (pdf)

Date Issued April 6, 1998
Reservoir Project Type Concurrent Production
Applicant Canadian Natural Resources Ltd. (CNRL)
Reservoir Field Buick Creek
Reservoir Formation Lower Halfway 'K'

 

CONCURRENT GEP CNRL Buick Creek Lower Halfway 'J' Amend 2 Oct-28-99 (pdf)

Date Issued October 28, 1999
Reservoir Project Type Concurrent Production
Applicant Canadian Natural Resources Ltd. (CNRL)
Reservoir Field Buick Creek
Reservoir Formation Lower Halfway 'J'

 

CONCURRENT GEP CNRL Buick Creek Lower Halfway 'J' Amend 1 May-08-97 (pdf)

Date Issued May 8, 1997
Reservoir Project Type Concurrent Production
Applicant Canadian Natural Resources Ltd. (CNRL)
Reservoir Field Buick Creek
Reservoir Formation Lower Halfway 'J'

 

CONCURRENT GEP CNRL Buick Creek Lower Halfway 'I' Feb-04-97 (pdf)

Date Issued February 4, 1997
Reservoir Project Type Concurrent Production
Applicant Canadian Natural Resources Ltd. (CNRL)
Reservoir Field Buick Creek
Reservoir Formation Lower Halfway 'I'

 

CONCURRENT GEP CNRL Buick Creek Lower Halfway 'E' Amend 1 Apr-03-96 (pdf)

Date Issued April 3, 1996
Reservoir Project Type Concurrent Production
Applicant Canadian Natural Resources Ltd. (CNRL)
Reservoir Field Buick Creek
Reservoir Formation Lower Halfway 'E'

 

CONCURRENT GEP CNRL Buick Creek Lower Halfway 'C', 'D', 'I' Dec-17-99 (pdf)

Date Issued December 17, 1999
Reservoir Project Type Concurrent Production
Applicant Canadian Natural Resources Ltd. (CNRL)
Reservoir Field Buick Creek
Reservoir Formation Lower Halfway 'C' 'D' 'I'

 

CONCURRENT GEP CNRL Buick Creek Lower Halfway 'C' Amend 7 Feb-24-04 (pdf)

Date Issued February 24, 2004
Reservoir Project Type Concurrent Production
Applicant Canadian Natural Resources Ltd. (CNRL)
Reservoir Field Buick Creek
Reservoir Formation Lower Halfway 'C'

 

CONCURRENT GEP CNRL Buick Creek Lower Halfway 'C' Amend 5 Sep-25-00 (pdf)

Date Issued September 25, 2000
Reservoir Project Type Concurrent Production
Applicant Canadian Natural Resources Ltd. (CNRL)
Reservoir Field Buick Creek
Reservoir Formation Lower Halfway 'C'

 

CONCURRENT GEP CNRL Buick Creek Lower Halfway 'B', 'E', 'H', 'J', 'K', 'N', 'O' May-01-00 (pdf)

Date Issued May 1, 2000
Reservoir Project Type Concurrent Production
Applicant Canadian Natural Resources Ltd. (CNRL)
Reservoir Field Buick Creek
Reservoir Formation Lower Halfway 'B' 'E' 'H' 'J' 'K' 'N' 'O'

 

CONCURRENT GEP CNRL Buick Creek Lower Halfway 'B', 'C', 'D', 'E', 'H', 'I', 'J', 'K', 'N', 'O' Aug-23-02 (pdf)

Date Issued August 23, 2002
Reservoir Project Type Concurrent Production
Applicant Canadian Natural Resources Ltd. (CNRL)
Reservoir Field Buick Creek
Reservoir Formation Lower Halfway 'B' 'C' 'D' 'E' 'H' 'I' 'J'

 

CONCURRENT GEP CNRL Buick Creek Lower Halfway 'B', 'C', 'D', 'E', 'H', 'I', 'J', 'K', 'N', 'O' Amend 6 Sep-12-02 (pdf)

Date Issued September 12, 2002
Reservoir Project Type Concurrent Production
Applicant Canadian Natural Resources Ltd. (CNRL)
Reservoir Field Buick Creek
Reservoir Formation Lower Halfway 'B' 'C' 'D' 'E' 'H' 'I' 'J'

 

CONCURRENT GEP CEGO Stoddart North Pine Bear Flat 'A' WA 5393 Apr-21-81 (pdf)

Date Issued April 21, 1981
Reservoir Project Type Concurrent Production
Applicant Placer CEGO Petroleum Limited
Reservoir Field Stoddart West
Reservoir Formation North Pine
WA Number 05393

 

CONCURRENT GEP CALAHOO Ft. St. John North Pine 'C' 'D' Amend 1 Nov-19-99 (pdf)

Date Issued November 19, 1999
Reservoir Project Type Concurrent Production
Applicant Calahoo Petroleum
Reservoir Field Fort St. John
Reservoir Formation North Pine

 

CONCURRENT GEP CALAHOO Ft. St. John North Pine 'A' Amend 3 Nov-19-99 (pdf)

Date Issued November 19, 1999
Reservoir Project Type Concurrent Production
Applicant Calahoo Petroleum
Reservoir Field Fort St. John
Reservoir Formation North Pine

 

CONCURRENT-GEP BP CANADA Beatton River Halfway 'B' Feb-22-89 (pdf)

Date Issued February 22, 1989
Reservoir Project Type Concurrent Production
Applicant BP Canada Energy Company
Reservoir Field Beatton River
Reservoir Formation Halfway 'B'

 

CONCURRENT GANE ENERGY Ft. St. John North Pine 'A' Nov-23-84 (pdf)

Date Issued November 23, 1984
Reservoir Project Type Concurrent Production
Applicant Gane Energy Corporation Ltd
Reservoir Field Fort St. John
Reservoir Formation North Pine

 

CONCURRENT FEKETE Eagle West Belloy 'C' Oct-06-03 (pdf)

Date Issued October 6, 2003
Reservoir Project Type Concurrent Production
Applicant Fekete Associates
Reservoir Field Eagle West
Reservoir Formation Belloy 'C'

 

CONCURRENT ENERMARK Flatrock Belloy 'A' Inisfail Talisman Flatrock WA 7497 Dec-17-04 (pdf)

Date Issued December 17, 2004
Reservoir Project Type Concurrent Production
Applicant Enermark Energy
Reservoir Field Flatrock
Reservoir Formation Belloy A
WA Number 07497

 

CONCURRENT ENCOR Muskrat Jul-16-92 (pdf)

Date Issued July 16, 1992
Reservoir Project Type Concurrent Production
Applicant Encor Inc.
Reservoir Field Muskrat
Reservoir Formation Halfway B Halfway C

 

CONCURRENT ENCANA Helmet Jean Marie 'K' Sep-12-03 (pdf)

Date Issued September 12, 2003
Reservoir Project Type Concurrent Production
Applicant Encana
Reservoir Field Helmet
Reservoir Formation Jean Marie 'K'

 

CONCURRENT ENCAL Zaremba A Marker Base of Lime 'M' Mar-07-01 (pdf)

Date Issued March 7, 2001
Reservoir Project Type Concurrent Production
Applicant Encal Energy Ltd.
Reservoir Field Zaremba
Reservoir Formation A Marker Base of Lime M

 

CONCURRENT ENCAL Zaremba Halfway 'I' May-07-98 (pdf)

Date Issued May 7, 1998
Reservoir Project Type Concurrent Production
Applicant Encal Energy Ltd.
Reservoir Field Zaremba
Reservoir Formation Halfway 'I'

 

CONCURRENT ENCAL W Milligan Creek West Halfway 'I' Jul-13-98 (pdf)

Date Issued July 13, 1998
Reservoir Project Type Concurrent Production
Applicant Encal Energy Ltd.
Reservoir Field Milligan Creek West
Reservoir Formation Halfway 'I'

 

CONCURRENT ENCAL W Milligan Creek West Halfway 'H' Jul-13-98 (pdf)

Date Issued July 13, 1998
Reservoir Project Type Concurrent Production
Applicant Encal Energy Ltd.
Reservoir Field Milligan Creek West
Reservoir Formation Halfway H

 

CONCURRENT ENCAL Flatrock West Halfway 'D' Aug-23-99 (pdf)

Date Issued August 23, 1999
Reservoir Project Type Concurrent Production
Applicant Encal Energy Ltd.
Reservoir Field Flatrock West
Reservoir Formation Halfway 'D'

 

CONCURRENT ENCAL Elm Gething 'B' Mar-20-01 (pdf)

Date Issued March 20, 2001
Reservoir Project Type Concurrent Production
Applicant Encal Energy Ltd.
Reservoir Field Elm
Reservoir Formation Gething B

 

CONCURRENT ENCAL Beatton River Halfway 'B' Amend 2 Dec-14-00 (pdf)

Date Issued December 14, 2000
Reservoir Project Type Concurrent Production
Applicant Encal Energy Ltd.
Reservoir Field Beatton River
Reservoir Formation Halfway 'B'

 

CONCURRENT DUVERNAY Groundbirch Cecil 'A' Oct-15-02 (pdf)

Date Issued October 15, 2002
Reservoir Project Type Concurrent Production
Applicant Duvernay Oil C
Reservoir Field Groundbirch
Reservoir Formation Cecil A

 

CONCURRENT DUVERNAY Groundbirch Cecil 'A' Amend 2 Mar-27-08 (pdf)

Date Issued March 27, 2008
Reservoir Project Type Concurrent Production
Applicant Duvernay Oil C
Reservoir Field Groundbirch
Reservoir Formation Cecil A

 

CONCURRENT DUVERNAY Groundbirch Cecil 'A' Amend 1 Mar-06-03 (pdf)

Date Issued March 6, 2003
Reservoir Project Type Concurrent Production
Applicant Duvernay Oil C
Reservoir Field Groundbirch
Reservoir Formation Cecil A

 

CONCURRENT DUVERNAY Groundbirch Artex 'B' Temp Modification Aug-26-03 (pdf)

Date Issued August 26, 2003
Reservoir Project Type Concurrent Production
Applicant Duvernay Oil C
Reservoir Field Groundbirch
Reservoir Formation Artex B

 

CONCURRENT DUVERNAY Groundbirch Artex 'B' Jun-03-02 (pdf)

Date Issued June 3, 2002
Reservoir Project Type Concurrent Production
Applicant Duvernay Oil C
Reservoir Field Groundbirch
Reservoir Formation Artex B

 

CONCURRENT DUVERNAY Groundbirch Artex 'B' Amend 1 Feb-05-04 (pdf)

Date Issued February 5, 2004
Reservoir Project Type Concurrent Production
Applicant Duvernay Oil C
Reservoir Field Groundbirch
Reservoir Formation Artex B

 

CONCURRENT DOMINION Cache Doig 'F' Aug-06-04 (pdf)

Date Issued August 6, 2004
Reservoir Project Type Concurrent Production
Applicant Dominion Exploration Canada LTd.
Reservoir Field Cache Creek
Reservoir Formation Doig 'F'

 

CONCURRENT DOMINION Cache Creek Doig 'C' Jan-28-04 (pdf)

Date Issued January 28, 2004
Reservoir Project Type Concurrent Production
Applicant Dominion Exploration Canada LTd.
Reservoir Field Cache Creek
Reservoir Formation Doig 'C'

 

CONCURRENT DOMINION Buick Creek N Dunlevy 'U' Jul-27-04 (pdf)

Date Issued July 27, 2004
Reservoir Project Type Concurrent Production
Applicant Dominion Exploration Canada LTd.
Reservoir Field Buick Creek North
Reservoir Formation Dunlevy U

 

CONCURRENT DOMINION Buick Creek N Dunlevy 'E' Dec-28-01 (pdf)

Date Issued December 28, 2001
Reservoir Project Type Concurrent Production
Applicant Dominion Exploration Canada LTd.
Reservoir Field Buick Creek North
Reservoir Formation Dunlevy E

 

CONCURRENT DOMINION Buick Creek N Dunlevy 'E' Amend 1 Aug-23-04 (pdf)

Date Issued August 23, 2004
Reservoir Project Type Concurrent Production
Applicant Dominion Exploration Canada LTd.
Reservoir Field Buick Creek North
Reservoir Formation Dunlevy E

 

CONCURRENT DEVON Bear Flat Bear Flat 'B' Sept-24-03 (pdf)

Date Issued September 24, 2003
Reservoir Project Type Concurrent Production
Applicant Devon Canada C
Reservoir Field Bear Flat
Reservoir Formation Bear Flat B

 

CONCURRENT DEVON Bear Flat Bear Flat 'B' and 'D' Aug-26-03 (pdf)

Date Issued August 26, 2003
Reservoir Project Type Concurrent Production
Applicant Devon Canada C
Reservoir Field Bear Flat
Reservoir Formation Bear Flat B and D

 

CONCURRENT DEVON Bear Flat Bear Flat 'B' and 'D' April-22-04 (pdf)

Date Issued April 22, 2013
Reservoir Project Type Concurrent Production
Applicant Devon Canada C
Reservoir Field Bear Flat
Reservoir Formation Bear Flat B and D

 

CONCURRENT CZAR Fireweed Nov-10-78 (pdf)

Date Issued November 10, 1978
Reservoir Project Type Concurrent Production
Applicant CZAR Resources Ltd.
Reservoir Field Fireweed
Reservoir Formation Doig

 

CONCURRENT CREW Laprise Coplin 'A' Jun-30-05 (pdf)

Date Issued June 30, 2005
Reservoir Project Type Concurrent Production
Applicant Crew Energy Ltd.
Reservoir Field Laprise Creek
Reservoir Formation Coplin A

 

CONCURRENT CREW Laprise Coplin 'A' Coplin 'B' Sep-15-04 (pdf)

Date Issued September 15, 2004
Reservoir Project Type Concurrent Production
Applicant Crew Energy Ltd.
Reservoir Field Laprise Creek
Reservoir Formation Coplin A Coplin B

 

CONCURRENT CREW Laprise Coplin 'B' May-14-07 (pdf)

Date Issued May 14, 2007
Reservoir Project Type Concurrent Production
Applicant Crew Energy Ltd.
Reservoir Field Laprise Creek
Reservoir Formation Coplin B

 

CONCURRENT CREW Laprise Coplin 'A' Amend 3 Aug-30-05 (pdf)

Date Issued August 30, 2005
Reservoir Project Type Concurrent Production
Applicant Crew Energy Ltd.
Reservoir Field Laprise Creek
Reservoir Formation Coplin A

 

CONCURRENT CREW Laprise Coplin 'A' Amend 2 Feb-16-05 (pdf)

Date Issued February 16, 2005
Reservoir Project Type Concurrent Production
Applicant Crew Energy Ltd.
Reservoir Field Laprise Creek
Reservoir Formation Coplin A

 

CONCURRENT CREW Laprise Coplin 'A' Amend 1 Nov-09-04 (pdf)

Date Issued November 9, 2004
Reservoir Project Type Concurrent Production
Applicant Crew Energy Ltd.
Reservoir Field Laprise Creek
Reservoir Formation Coplin A

 

CONCURRENT COMMINGLED PETROCAN Boundary Lake Halfway 'E', L Halfway 'A' 'B' Aug-27-03 (pdf)

Date Issued August 27, 2003
Reservoir Project Type Concurrent Production
Applicant Petrocan
Reservoir Field Boundary Lake
Reservoir Formation Halfway 'E' Lower Halfway 'A' 'B'

 

CONCURRENT COM BERKLEY Halfway Coplin 'A', Inga 'A' Blueberry 'A' May-24-00 (pdf)

Date Issued May 24, 2000
Reservoir Project Type Concurrent Production
Applicant Berkley Petroleum Corp.
Reservoir Field Halfway
Reservoir Formation Coplin A Inga A Blueberry A