Concurrent Pengrowth Corporatio Weasel Gething F River (pdf)
| Date Issued |
January 28, 2008 |
| Deadline Date |
February 18, 2008 |
| Reservoir Project Type | Concurrent Production |
| Applicant | Pengrowth Corporatio |
| Reservoir Field | Weasel |
| Reservoir Formation | Gething F River |
Concurrent Production Pengrowth Corporatio Squirrel Bluesky A (pdf)
| Date Issued |
August 20, 2007 |
| Deadline Date |
September 11, 2007 |
| Reservoir Project Type | Concurrent Production |
| Applicant | Pengrowth Corporatio |
| Reservoir Field | Squirrel |
| Reservoir Formation | Bluesky A |
Concurrent Production Approval Pavilion Energ Rigel Halfway C (pdf)
| Date Issued |
October 30, 2007 |
| Deadline Date |
November 20, 2007 |
| Reservoir Project Type | Concurrent Production |
| Applicant | Pavilion Energ |
| Reservoir Field | Rigel |
| Reservoir Formation | Halfway C |
Concurrent Production KXL Exploration Ltd. Boundary Lake Halfway (pdf)
| Date Issued |
January 9, 2012 |
| Deadline Date |
January 30, 2012 |
| Reservoir Project Type | Concurrent Production |
| Applicant | KXL Exploration Ltd. |
| Reservoir Field | Boundary Lake |
| Reservoir Formation | Halfway |
Concurrent Production KXL Exploration Ltd. Boundary Lake Halfway K and M (pdf)
| Date Issued |
August 31, 2010 |
| Deadline Date |
September 22, 2010 |
| Reservoir Project Type | Concurrent Production |
| Applicant | KXL Exploration Ltd. |
| Reservoir Field | Boundary Lake |
| Reservoir Formation | Halfway K and M |
Good Engineering Practice and Concurrent Production EnCana Corpora Maxhamish Lake Chinkeh A (pdf)
| Date Issued |
May 16, 2007 |
| Deadline Date |
June 6, 2007 |
| Reservoir Project Type | Good Engineering Practice |
| Applicant | EnCana Corpora |
| Reservoir Field | Maxhamish Lake |
| Reservoir Formation | Chinkeh A |
Concurrent Production Bonavista Petroleum Ltd. Buick Creek Dunlevy C (pdf)
| Date Issued |
May 5, 2010 |
| Deadline Date |
May 26, 2010 |
| Reservoir Project Type | Concurrent Production |
| Applicant | Bonavista Petroleum Ltd. |
| Reservoir Field | Buick Creek |
| Reservoir Formation | Dunlevy C |
Concurrent Production Approval Baytex Energy Cache Creek Doig T (pdf)
| Date Issued |
September 18, 2007 |
| Deadline Date |
October 9, 2007 |
| Reservoir Project Type | Concurrent Production |
| Applicant | Baytex Energy |
| Reservoir Field | Cache Creek |
| Reservoir Formation | Doig T |
CONCURRENT CNRL Helmet Tetcho Notice Nov-20-14 (pdf)
| Date Issued |
November 21, 2014 |
| Deadline Date |
December 11, 2014 |
| Reservoir Project Type | Concurrent Production |
| Applicant | Canadian Natural Resources Limited |
| Reservoir Field | Helmet |
| Reservoir Formation | Tetcho |
CONCURRENT CNRL Dunlevy 'B' Siphon East Nov-25-14 (pdf)
| Date Issued |
November 27, 2014 |
| Deadline Date |
December 16, 2014 |
| Reservoir Project Type | Concurrent Production |
| Applicant | Canadian Natural Resources Ltd. (CNRL) |
| Reservoir Field | Dunlevy 'B' |
| Reservoir Formation | Siphon East |
CONCURRENT AITKEN CREEK GAS Aitken Creek North Sep-11-18 (pdf)
| Date Issued |
September 11, 2018 |
| Deadline Date |
October 2, 2018 |
| Reservoir Project Type | Concurrent Production |
| Applicant | Aitken Creek Gas Storage ULC |
| Reservoir Field | Aitken Creek North |
27314_APPR_2018DEC06_APPLICATION FOR SALT WATER DISPOSAL (pdf)
| Date Issued |
December 7, 2018 |
| Deadline Date |
December 7, 2018 |
| Reservoir Project Type | Produced Water Disposal |
| Applicant | Canadian Natural Resources Limited |
| Reservoir Field | Septimus |
| Reservoir Formation | Cadomin |
| WA Number | 27314 |
Coal Bed Methane Hudson's hope (pdf)
| Date Issued |
September 5, 2007 |
| Deadline Date |
September 26, 2007 |
| Reservoir Project Type | Coal Bed Methane |
| Applicant | Hudson's hope |
| Reservoir Field | Hudson's Hope |
| Reservoir Formation | Gething |
Experimental Scheme Canada Spirit Farrel Creek Gething (pdf)
| Date Issued |
October 10, 2007 |
| Deadline Date |
October 31, 2007 |
| Reservoir Project Type | Experimental Scheme / Innovative Technology |
| Applicant | Canada Spirit |
| Reservoir Field | Farrel Creek |
| Reservoir Formation | Gething |
SWD Catapult Tower Cadomin Nikanassin WA20155 Aug 9/18 Notice (pdf)
| Date Issued |
August 9, 2018 |
| Deadline Date |
August 30, 2018 |
| Reservoir Project Type | Produced Water Disposal |
| Applicant | Catapult Environmental Inc. |
| Reservoir Field | Tower Lake |
| Reservoir Formation | Cadomin |
| WA Number | 20155 |
GEP Good Engineering Practice ProEx Energy Ltd. Caribou Halfway (pdf)
| Date Issued |
June 30, 2008 |
| Deadline Date |
July 21, 2008 |
| Reservoir Project Type | Good Engineering Practice |
| Applicant | ProEx Energy Ltd. |
| Reservoir Field | Caribou |
| Reservoir Formation | Halfway |
ACID GAS DISPOSAL Talisman Energy Inc. Pardonet Baldonnel "B" (pdf)
| Date Issued |
January 25, 2010 |
| Deadline Date |
February 15, 2010 |
| Reservoir Project Type | Acid Gas Disposal |
| Applicant | Talisman Energy Inc. |
| Reservoir Field | Pardonet |
| Reservoir Formation | Baldonnel |
Acid Gas Disposal Murphy Oil Company Ltd. Sundown Baldonnel (pdf)
| Date Issued |
April 30, 2010 |
| Deadline Date |
May 21, 2010 |
| Reservoir Project Type | Acid Gas Disposal |
| Applicant | Murphy Oil Company Ltd. |
| Reservoir Field | Sundown |
| Reservoir Formation | Baldonnel |
Amend Acid Gas Disposal Scheme Fekete Associates Jedney Baldonnel A (pdf)
| Date Issued |
September 11, 2012 |
| Deadline Date |
October 1, 2012 |
| Reservoir Project Type | Acid Gas Disposal |
| Applicant | Fekete Associates |
| Reservoir Field | Jedney |
| Reservoir Formation | Baldonnel A |
Acid Gas Disposal Amendment Keyera Energy Caribou Debolt "A" (pdf)
| Date Issued |
July 28, 2008 |
| Deadline Date |
August 15, 2008 |
| Reservoir Project Type | Acid Gas Disposal |
| Applicant | Keyera Energy |
| Reservoir Field | Caribou |
| Reservoir Formation | Debolt "A" |
Acid Gas Disposal ConocoPhillips Ring Debolt (pdf)
| Date Issued |
March 2, 2010 |
| Deadline Date |
March 22, 2010 |
| Reservoir Project Type | Acid Gas Disposal |
| Applicant | ConocoPhillips |
| Reservoir Field | Ring |
| Reservoir Formation | Debolt |
Acid Gas Disposal ARC Petroleum Inc. Dawson Belloy (pdf)
| Date Issued |
April 23, 2010 |
| Deadline Date |
May 14, 2010 |
| Reservoir Project Type | Acid Gas Disposal |
| Applicant | ARC Petroleum Inc. |
| Reservoir Field | Dawson |
| Reservoir Formation | Belloy |
ACID GAS STORM Nig Creek Halfway WA 37395 Oct-17-19 (pdf)
| Date Issued |
October 17, 2019 |
| Deadline Date |
November 7, 2019 |
| Reservoir Project Type | Acid Gas Disposal |
| Applicant | Storm Resources Ltd. |
| Reservoir Field | Nig Creek |
| Reservoir Formation | Halfway |
| WA Number | 37395 |
ACID GAS LEUCROTTA Doe Belloy WA 30630 Notice (pdf)
| Date Issued |
March 25, 2015 |
| Deadline Date |
April 17, 2015 |
| Reservoir Project Type | Acid Gas Disposal |
| Applicant | Leucrotta |
| Reservoir Field | Doe |
| Reservoir Formation | Belloy |
| WA Number | 30630 |
ACID GAS CNRL W Stoddart Doig E WA 10347 Jan-11-17 Notice (pdf)
| Date Issued |
January 11, 2017 |
| Deadline Date |
February 1, 2017 |
| Reservoir Project Type | Acid Gas Disposal |
| Applicant | Canadian Natural Resources Limited |
| Reservoir Field | West Stoddart |
| Reservoir Formation | Doig E |
| WA Number | 10347 |
ACID GAS ARC Doe Belloy WA 30922 Oct-18-16 Notice (pdf)
| Date Issued |
October 18, 2016 |
| Deadline Date |
November 8, 2016 |
| Reservoir Project Type | Acid Gas Disposal |
| Applicant | ARC Resources Ltd. |
| Reservoir Field | Doe |
| Reservoir Formation | Belloy |
| WA Number | 30922 |
GEP Sauaro Laprise creek (pdf)
| Date Issued |
December 20, 2013 |
| Deadline Date |
January 10, 2014 |
| Reservoir Project Type | Good Engineering Practice |
| Applicant | Saguaro Resources Ltd |
| Reservoir Field | Laprise Creek |
| Reservoir Formation | Montney |
GEP NORTHPOINT Altares Gething Notice Oct-2-13 (pdf)
| Date Issued |
October 9, 2013 |
| Deadline Date |
October 30, 2013 |
| Reservoir Project Type | Good Engineering Practice |
| Applicant | Northpoint Energy Lt |
| Reservoir Field | Altares |
| Reservoir Formation | Gething |
29046_APPR_GEN Nexen Liard Horn River Shale Apr-17-15 (pdf)
| Date Issued |
April 21, 2015 |
| Deadline Date |
April 21, 2015 |
| Reservoir Project Type | General |
| Applicant | Nexen Inc. |
| Reservoir Field | Liard |
| Reservoir Formation | Horn River Shale |
| WA Number | 29046 |
28288_APPR_GEN Nexen Liard Horn River Shale Apr-17-15 (pdf)
| Date Issued |
April 21, 2015 |
| Deadline Date |
April 21, 2015 |
| Reservoir Project Type | General |
| Applicant | Nexen |
| Reservoir Field | Liard |
| Reservoir Formation | Horn River Shale |
| WA Number | 28288 |