Approval documents available include both orders and explanatory cover letters for: waterflood (pressure maintenance), gas injection, innovative technology (experimental), Good Engineering Practice, disposal wells, observation wells, Concurrent Production, commingled production, and gascap blowdown.
These records span from 1964 to present-date and include any amendments made to an approval, as well as denial letters. Applications for these approvals may be requested by submission of a well data request form. The company name is that at the time of correspondence, and may not reflect the current well permit holder. The filter function allows partial entry of a single data field as search criteria.
Date Issued:
PM WHITECAP Boundary Lake Boundary Lake A Amend 16 Sep-21-17 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Whitecap Resources Inc. |
| Reservoir Field | Boundary Lake |
| Reservoir Formation | Boundary Lake A |
Date Issued:
PM CNRL Birch Baldonnel C Amend 4 Sep-15-17 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Canadian Natural Resources Limited |
| Reservoir Field | Birch |
| Reservoir Formation | Baldonnel |
Date Issued:
PM CNRL Eagle West Belloy A Amend 7 Jul-31-17 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Canadian Natural Resources Limited |
| Reservoir Field | Eagle West |
| Reservoir Formation | Belloy A |
Date Issued:
PM WHITECAP Boundary Lake Boundary Lake A Amend 15 Jul-31-17 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Whitecap Resources Inc. |
| Reservoir Field | Boundary Lake |
| Reservoir Formation | Boundary Lake A |
Date Issued:
PM Pavilion Red Creek Doig C Amend 3 Jun-30-17 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Pavilion Energy Corporation |
| Reservoir Field | Red Creek |
| Reservoir Formation | Doig C |
Date Issued:
PM VENTURION Mica Mica A Amend 3 Apr-3-17 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Venturion Oil Limited |
| Reservoir Field | Mica |
| Reservoir Formation | Mica A |
Date Issued:
PM PENGROWTH Beatton River Halfway A Feb-01-17 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Pengrowth Energy Corporation |
| Reservoir Field | Beatton River |
| Reservoir Formation | Halfway A |
Date Issued:
PM PENGROWTH Oak Cecil C Amend 3 Sep-12-16 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Pengrowth Energy Corporation |
| Reservoir Field | Oak |
| Reservoir Formation | Cecil C |
Date Issued:
PM CNRL Birch Baldonnel 'C' Amend 3 Jul-6-16 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Canadian Natural Resources Limited |
| Reservoir Field | Birch |
| Reservoir Formation | Baldonnel 'C' |
Date Issued:
PM DEJOUR Woodrush Halfway 'E' Amend 3 Apr-1-16 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | DXI Energy Inc. |
| Reservoir Field | Woodrush |
| Reservoir Formation | Halfway E |
Date Issued:
PM PENGROWTH Rigel Cecil 'G' Amend 4 Mar-30-16 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Pengrowth Energy Corporation |
| Reservoir Field | Rigel |
| Reservoir Formation | Cecil 'G' |
Date Issued:
PM Pengrowth Stoddart North Pine 'G' Mar-24-16 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Pengrowth Corporation |
| Reservoir Field | Stoddart |
| Reservoir Formation | North Pine G |
| WA Number | 14331 |
Date Issued:
PM Dejour Woodrush Halfway 'E' Mar-24-16 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | DXI Energy Inc. |
| Reservoir Field | Woodrush |
| Reservoir Formation | Halfway E |
| WA Number | 30889 |
Date Issued:
PM PENGROWTH Elm Gething 'B' Amend 1 Mar-24-16 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Pengrowth Energy Corporation |
| Reservoir Field | Elm |
| Reservoir Formation | Gething B |
Date Issued:
PM WHITECAP Boundary Lake Boundary Lake 'A' Mar-17-16 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Whitecap Resources Inc. |
| Reservoir Field | Boundary Lake |
| Reservoir Formation | Boundary Lake A |
Date Issued:
PM HARVEST Hay River Bluesky 'A' Amend 10 Dec-15-5 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Harvest Operations Corp. |
| Reservoir Field | Hay River |
| Reservoir Formation | Bluesky |
Date Issued:
PM HARVEST Hay River Bluesky 'A' Amend 9 Jun-30-15 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Harvest Operations Corp. |
| Reservoir Field | Hay River |
| Reservoir Formation | Bluesky 'A' |
Date Issued:
PM CNRL Buick Creek Lower Halfway 'C' Mar-10-15 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Canadian Natural Resources Ltd. (CNRL) |
| Reservoir Field | Buick Creek |
| Reservoir Formation | Lower Halfway 'C' |
Date Issued:
PM VENTURION Boundary Lake North Field Halfway 'D' 'I' Dec-12-14 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Venturion |
| Reservoir Field | Boundary Lake North |
| Reservoir Formation | Halfway 'D' 'I' |
Date Issued:
PM CNRL Lapp Halfway 'D' Amend 3 Dec-05-14 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Canadian Natural Resources Ltd. (CNRL) |
| Reservoir Field | Lapp |
| Reservoir Formation | Halfway 'D' |
Date Issued:
PM HARVEST Hay River Bluesky 'A' Oct-27-14 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Harvest Operation Co |
| Reservoir Field | Hay River |
| Reservoir Formation | Bluesky |
Date Issued:
PM CNRL Peejay West Halfway 'C' Amend 2 Jan-13-14 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | CNRL |
| Reservoir Field | Peejay |
| Reservoir Formation | Halfway 'C' |
Date Issued:
PM CARMEL BAY EXPLORATION Mica Mica 'A' Amend 2 Sep-27-13 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Carmel Bay |
| Reservoir Field | Mica |
| Reservoir Formation | Mica |
Date Issued:
PM PENGROWTH Oak Rigel Various pools Aug-21-13 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Pengrowth Corporatio |
| Reservoir Field | Oak |
| Reservoir Formation | Rigel |
Date Issued:
PM PROGRESS Blueberry Debolt E May-10-13 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Progress Energy |
| Reservoir Field | Blueberry |
| Reservoir Formation | Debolt |
Date Issued:
PM OTN CARMEL BAY Gas Injection Mica Mica A Oil May-8-13 Amend 1 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Carmel Bay |
| Reservoir Field | Mica |
| Reservoir Formation | Mica |
Date Issued:
PM OTN CNRL Peejay W Halfway A Apr-11-13 Amend 4 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Canadian Natural Resources Ltd. (CNRL) |
| Reservoir Field | Peejay West |
| Reservoir Formation | Halfway 'A' |
Date Issued:
PM Waterflood CNRL Peejay West Halfway A oil Feb-26-13 Amend (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Canadian Natural Resources Ltd. (CNRL) |
| Reservoir Field | Peejay West |
| Reservoir Formation | Halfway 'A' |
Date Issued:
PM CNRL Birch Baldonnel C Jan-10-13 Amend 2 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Canadian Natural Resources Ltd. (CNRL) |
| Reservoir Field | Birch |
| Reservoir Formation | Baldonnel C |
Date Issued:
PM CNRL Birch Baldonnel C Jan-7-13 Amend 2 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Canadian Natural Resources Ltd. (CNRL) |
| Reservoir Field | Birch |
| Reservoir Formation | Baldonnel C |
Date Issued:
PM OTN CNRL Beavertail Halfway H Dec-13-12 Amend 3 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Canadian Natural Resources Ltd. (CNRL) |
| Reservoir Field | Beavertail |
| Reservoir Formation | Halfway H |
Date Issued:
PM HARVEST WATERFLOOD Hay River Bluesky 'A' Amend 8 Jul-11-12 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Harvest Operation Co |
| Reservoir Field | Hay River |
| Reservoir Formation | Bluesky 'A' |
Date Issued:
PM CNRL Birch Field Baldonnel 'C' Amend 1 May-24-12 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Canadian Natural Resources Ltd. (CNRL) |
| Reservoir Field | Birch |
| Reservoir Formation | Baldonnel C |
Date Issued:
PM STORM Mica Mica 'A' Feb-09-12 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Storm |
| Reservoir Field | Mica |
| Reservoir Formation | Mica A |
Date Issued:
PM DEJOUR Woodrush Halfway E Amend 2 Oct-11-11 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Dejour Energy Ltd. |
| Reservoir Field | Woodrush |
| Reservoir Formation | Halfway E |
Date Issued:
PM PROCYON Rigel Dunlevy 'A' Oct-06-11 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Procyon Energy Corp. |
| Reservoir Field | Rigel |
| Reservoir Formation | Dunlevy 'A' |
Date Issued:
PM TAQA Boundary Lake Boundary 'A' Amend 7 Aug-08-11 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | TAQA North Ltd. |
| Reservoir Field | Boundary Lake |
| Reservoir Formation | Boundary Lake A |
Date Issued:
PM TERRA Red Creek Doig C Amend 2 Mar-28-11 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Terra Energy Corp. |
| Reservoir Field | Red Creek |
| Reservoir Formation | Doig 'C' |
Date Issued:
PM DEJOUR Woodrush Halfway E Amend 1 Mar-23-11 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Dejour Energy Ltd. |
| Reservoir Field | Woodrush |
| Reservoir Formation | Halfway E |
Date Issued:
PM CNRL Peejay West Halfway 'A' Amend 3 Mar-02-11 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Canadian Natural Resources Ltd. (CNRL) |
| Reservoir Field | Peejay West |
| Reservoir Formation | Halfway 'A' |
Date Issued:
PM DEJOUR Woodrush Halfway E Dec-16-10 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Dejour Energy Ltd. |
| Reservoir Field | Woodrush |
| Reservoir Formation | Halfway E |
Date Issued:
PM HUNT Rigel Halfway H Nov-01-10 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Hunt Oil Company of Canada Inc. |
| Reservoir Field | Rigel |
| Reservoir Formation | Halfway H |
Date Issued:
PM HUNT Rigel Halfway H WA 11650 Oct-27-10 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Hunt Oil Company of Canada Inc. |
| Reservoir Field | Rigel |
| Reservoir Formation | Halfway H |
| WA Number | 11650 |
Date Issued:
PM PROGRESS Two Rivers Siphon 'A' Amend 2 Oct-15-10 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Progress Energy |
| Reservoir Field | Two Rivers |
| Reservoir Formation | Siphon |
Date Issued:
PM Bonavista Buick Creek West Dunlevy Oct-14-10 Order (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Bonavista Petroleum |
| Reservoir Field | Buick Creek West |
| Reservoir Formation | Dunlevy |
Date Issued:
PM PENGROWTH Squirrel North Pine 'C' Amend 7 Jun-23-10 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Pengrowth Corporation |
| Reservoir Field | Squirrel |
| Reservoir Formation | North Pine |
Date Issued:
PM CNRL Beatton River West Unit 1- Bluesky A Apr-30-10 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Canadian Natural Resources Ltd. (CNRL) |
| Reservoir Field | Beatton River West |
| Reservoir Formation | Bluesky 'A' |
Date Issued:
PM CNRL Beatton River West Bluesky 'A' Amend Apr-01-10 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Canadian Natural Resources Ltd. (CNRL) |
| Reservoir Field | Beatton River West |
| Reservoir Formation | Bluesky 'A' |
Date Issued:
PM DEVON Stoddart West- Belloy C Apr-01-10 Amend 6 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Devon Canada C |
| Reservoir Field | Stoddart West |
| Reservoir Formation | Belloy 'C' |
Date Issued:
PM CENTRAL GLOBAL Oak Cecil 'I' Amend 3 Feb-04-10 (pdf)
| Reservoir Project Type | Pressure Maintenance Waterflood or Pressure Maintenance Gas Injection |
| Applicant | Central Global |
| Reservoir Field | Oak |
| Reservoir Formation | Cecil I |